West Hartford Center Farmington Avenue Construction: What's Opening Next

  • October 22, 2026

The Town's reconstruction of Farmington Avenue and LaSalle Road is due to finish by November 20, 2026. Most people have tracked two seasons of work by which sidewalk they had to walk around. Taken in order, a few businesses opened while the work was underway. A few moved within the Center while it went on. The biggest project on the block, the old CVS building at 976-978 Farmington Avenue, could not start rising until the street work in front of it was done.

So the openings coming in December are timed by the street work.

Where the Barriers Still Stand

The Town describes the project as resurfacing, granite curbs, wider concrete sidewalks, decorative street lighting, signal changes, landscaped tree pits, raised crosswalks and new site furniture. It covers Farmington Avenue from North and South Main Street to Walden Street, and LaSalle Road from Farmington Avenue to Ellsworth Road. In late September, We-Ha reported the project was about 85 percent complete as of September 25.

We-Ha walked the block on October 7. Here is what it found:

Stretch Status on October 7, 2026
Corner of Farmington Avenue and South Main Street Almost fully complete
Sidewalk in front of Sparrow One very small section still blocked; outdoor tables back out
Between Barcelona/bartaco and Westfield Bank Last sidewalk demolition underway

That last stretch is where the remaining work is. The Town's two-week look-ahead dated October 5 scheduled sidewalk demolition and pours in front of businesses for October 12 through 16. It also said the project team would try to keep business entrances open and safe. The Town calls every date on its project schedule tentative and subject to weather and field conditions. The Town posts its progress notes on the construction updates page.

Parking is still tight at the margins. The Town's plan uses the Arapahoe lot as a contractor laydown area. To keep on-street spaces open for visitors, it is asking Center employees to use the Town Center Garage. Rates there are $4.50 for up to an 8.5-hour shift and $7 for longer.

The Shops That Opened Mid-Construction

Over the summer, several owners opened while the barriers were still up.

  • The Brownstone, a pizza restaurant at 7 South Main Street, announced a soft opening for July 28, according to We-Ha's July 20 column. We-Ha's August 3 column still described it as in its soft-opening phase.
  • Kathryn Hunt Studio held a grand opening at 970 Farmington Avenue the week before We-Ha's July 20 column. It added a retail showroom on the ground floor and moved its design studio upstairs.
  • Bliss Matcha & Beyond soft-opened at 981 Farmington Avenue on Saturday, August 1, We-Ha reported. Its Chamber ribbon-cutting followed on August 7.
  • Lil Hope moved from 18 LaSalle Road to 990 Farmington Avenue and was open at the new address by late August, according to We-Ha's August 24 column.

Bliss Matcha opened on the stretch where the sidewalks were being rebuilt. In late September, We-Ha listed the area by Sparrow, J.McLaughlin and Bliss Matcha & Beyond among the sections that had moved furthest along.

Moves inside the Center also free up space. Once Lil Hope left 18 LaSalle Road, Salt Studio, described in Town permitting as a nail and esthetics salon, began permitting for that address, We-Ha reported in early October. No opening date has been announced. Gveenah plans to move within its building, from 844 to 846 Farmington Avenue. As of early October it was still listed at 844.

Why the Old CVS Waited for the Street

Market Hospitality Group plans to turn the 1930s building at 976-978 Farmington Avenue, once home to CVS and Max Zeller Furs, into two restaurants with a new second story above them holding five apartments. The restaurants are Mercato and Blu Pointe.

The street project moves underground utilities as well as sidewalks. In We-Ha's September 21 column, co-owner Eli Hawli said the building work had been on hold while construction went on directly in front of it. The project needed new water, sewer and electric connections, and that work has now been finished. In the meantime, crews have been pouring the foundation footings.

Now that those connections are in, the timeline is moving quickly. Hawli told We-Ha he expected steel to go up within a few weeks. The second story should be framed and weather-tight soon after, with the apartments and the restaurant interiors built at the same time.

"We hope one restaurant will be open by the end of December," Hawli told We-Ha, with the second following fairly soon after. "Once the steel is up, our teams are ready to build. Full speed ahead."

He also said the design hasn't changed from the earlier renderings, apart from the sidewalk, which has changed since those drawings were made. "Farmington Avenue looks much better," he said. On the menus, the group's website describes Mercato as a scratch kitchen serving pasta, pizza, salads and Italian dishes. Blu Pointe, which Hawli said will be the first in Connecticut, serves seasonal steak and seafood, including sushi. The group opened a Mercato in Cheshire earlier in September.

What's Next in Line

The Center's other upcoming openings are at different stages. Here they are, from closest to opening to furthest:

  1. Blu Olive, a Mediterranean restaurant with an Italian focus, is next door to its sister restaurant Harvest on LaSalle Road. In late September, Harvest staff told We-Ha it was a few weeks from opening, and the room looked close to finished through the window.
  2. Mercato and Blu Pointe, at 976-978 Farmington Avenue, are aiming for one opening by the end of December and the second soon after.
  3. The former Cookshop Plus space on LaSalle Road is getting a new concept from Le Mazet owner Jared Cohen and a former business partner from Republic. Cohen told We-Ha it would be a few months before he shares details.
  4. El Pollo Guapo is coming to the former Kitchen Plate and Boston Market space at 1240 Farmington Avenue in Sunset Triangle. Its window sign is up, but no opening date has been set, per We-Ha.

The Center's Calendar to December

Two community events fall on either side of the November 20 completion target. Between them you can see the block go from active work zone to finished street.

Saturday, October 24, 10:30 a.m. to 12:30 p.m. The Moms & More Club of West Hartford Halloween Stroll brings costumed trick-or-treaters through Blue Back Square and West Hartford Center, with giveaways, treats and music along the way. The rain date is Sunday, October 25. The event listing notes that it gets packed. Since the last sidewalk work is between Barcelona/bartaco and Westfield Bank, some of this year's route may still pass active work areas.

October 29 through November 1. World of Beer at Blue Back Square runs WOB-O-WEEN, with a costume competition, live music and themed drinks.

November 20. This is the Town's target date for finishing the project.

Thursday, December 3. The West Hartford Chamber's 39th annual Holiday Stroll fills Blue Back Square and the Center with Santa, restaurant samples, a community Menorah Lighting, live performances, Victorian carolers and fire trucks to look at. It is organized by the Town, Blue Back Square, the Chamber and the West Hartford Center Business Association. If the Town hits its target, this will be the first big event of the year on the finished sidewalks.

Over the summer, much of the Center's foot traffic moved to Blue Back Square, which we wrote about in West Hartford's summer running through Blue Back Square. A different street showed how a block's activity can live in its storefronts, in Park Road Lost Its Parade. It Didn't Lose Its Crowd. This season, the Center's own sidewalks are the ones reopening. For more on the town as a whole, see our West Hartford neighborhood page.

New sidewalks, new lighting and a full restaurant row change how a block looks, and buyers notice. If you own near the Center and are wondering how this winter's finished Farmington Avenue might affect your home's value next spring, Laurie Kane Real Estate can walk through it with you. Request your complimentary CMA & staging consultation, and we'll look at what your home's setting adds now that the barriers are coming down.

Work With Laurie

Laurie's dedication to helping you achieve your real estate goals is truly commendable. By offering her expertise in choosing the perfect color palette and staging your home to enhance its marketability, she ensures that every aspect of the selling process is optimized for success. With her keen eye for design and a deep understanding of what buyers are looking for, Laurie can transform your home into a show-stopping masterpiece that captures the attention of potential buyers and helps you achieve top dollar for your property.